SOMCES Company Building projects
No. | Project Name | Completio n date | Contract Sum (USD) | Name of Client and address |
1 | SSFPL-026-W02/ PNTB/82/2019 Construction of visitors’ reception building and completion of a multipurpose hall at the Ministry of State Compound, Garowe, Puntland | Ongoing | USD $ 514,380.83 | Somali Stability Fund
[SSF] |
2 | Rehabilitation of SCAA building in SCAA compound at Aden Abdulle International Airport, Mogadishu – Somalia. | 05 April,
2020 |
$ 122,196
USD |
Somali Civil Aviation Authority (SCAA) |
3 | Drilling and Equipping of boreholes and Construction of Water supply system components in Xumbays, Bari, Puntland. | April 30,
2020 |
$147,882.28 | UNICEF – Somalia |
4 | Construction/Rehabilitation of Agricultural Infrastructures in Selected Sites in Beledweyne District | October 2019 | $174,694 | SYPD with the funding agent of SSF – Somalia |
5 | Construction of Jubaland Representative house in Kismayo – Somalia | August 2019 | $241,062.19 | UNDP – Somalia |
6 | Gahair Campus Rehabilitations for SIMAD University | February 2019 | $ 25,650 | SIMAD University |
7 | Rehabilitation works for SIMAD University Gahair Campus | Oct. 2018 | $ 8,914.96 | SIMAD University |
8 | Kitchen Renovation and Berked Construction at Mogadishu Central Prison | August, 2018 | $ 9,751 | ICRC – Mogadishu |
9 | Construction of THREE Fish drying Facilities with drainage system to Small Methane digester in
Kismaayo – Somalia |
Oct. 2018 | $ 91,577.70 | UNDP – Somalia |
10 | Construction of Borehole Facility rooms, Water Kiosks, and Animal troughs, Installation of water pipelines in RakoRaxo, Nugaal Region – Somalia | June, 2018 | $153,955.96 |
Somalia Stability Fund (SSF). |
11 | Drilling, Casing, Capping and Equipping of a Second New borehole and construction of Elevated Water
Tank in RakoRaxo, Nugaal Region – Somalia |
April, 2018 | $394,980.00 |
Somali Stability Fund [SSF] |
12 | Rehabilitation of Bukuraale Canal at Jowhar, Somalia | December 2017 | $ 60,997.65 | UNDP, Somalia |
13 | Construction of Mogadishu Central prison Vocational Training Centre | October, 2017 | $ 172,067 | The International Committee of the |
14 | Construction of Aden Adde International University – AAIU – Campus | October, 2017 | 125,650 | AAIU, Mogadishu
– Somalia |
15 | Construction of Library Hall for Somali National University SNU, funded by DRC Diaspora program
through SOCDA organization |
30/06/2017 | $ 57,360.66 | DRC – Diaspora Program through
SOCDA, Mogadishu |
16 | Construction of Borehole Supporting facilities and Installation of water distribution pipelines to the villages in: Towfiq, Ceelbub, Dhudhub, Xiriiro & Rakko-Raaxo in
Puntland, Somalia. Contract Number GD-PL-15 |
30 Nov 2016 |
$ 410,719.80 |
Adam Smith International Africa Limited, Representing the
Somalia Stability Fund |
17 | Drilling, Casing, Capping and Equipping of a borehole in Rako-raxo (500m), Puntland, Somalia.
Number GD-PL-09/1 (Lot 2). in reference a Contract Agreement (the Agreement) reference number GD-PL-09/1 (Lot 1) made on the 16th day of December 2015 together with an amendment to the contract (Amendment 1) |
30
September 2016 |
$ 571,350 |
Adam Smith International Africa Limited,
Representing the Somalia Stability Fund (SSF). |
18 | Drilling, Casing, Capping and Equipping of a borehole in Tawfiq, Puntland State, Somalia Contract Number GD-PL-09/1 (Lot 1)
(the work including construction of 50 meter cubic elevated water tank, two operation rooms, solar system for the borehole) |
30 June,
2016 |
151,304.80 | Somalia Stability Fund (SSF) |
19 | Consultancy works for various infrastructure works and Rehabilitation of Borehole wells in Mogadishu and
Jowhar middle shabelle region |
June, 2016 | $83,723 | SOPHPA |
20 | Construction & Rehabilitation works of Wadajir &
Hanale health centres (Demolishing partition walls, adding new rooms, rehabilitation all sections in the MCH and flooring improvement) |
30 March
2016 |
$ 23,999.24 | CESVI |
21 | Construction and rehabilitation of Bur-hindi road in Warta-nabadda district | Feb-2015 | 133,599.64 | IOM, Mogadishu, Somalia |
22 | Engineering Surveying practical workshop with Jamhuriya University for faculty of engineering students | March-2015 | 5,350 | Jamhuriya University ”JUST” |
23 | Consulting works for developing detailed
architectural, structural and BOQs for Mandheere health clinic in Jowhar District |
August 2015 | 22,850 | International Committee of the Red Cross “ICRC” |
24 | Construction and rehabilitation works of Muntada Guest house | Dec- 2014 | 35,600 | Almuntada, Mogadishu |
25 | Drilling a Borehole in Galkayo city (the work included water piping installation, construction of storage tank, Pump installation and Generator) | Sept. 2012 | 175,123.60 | Muslim Hands, Puntland office |